Demolition of the Suojrinne service building

The city of Äänekoski is demolishing the empty former Suojarinne service center in Suolahti.
A building in poor condition. Guardrail 21 has been left empty, and it is not profitable to repair it. The construction site will start with fencing the area and interior demolition work. A noise permit has also been applied for the demolition.
The operation of the city's central kitchen, which is closed in the building, is taken into account in the demolition work, and the demolition has no effect on the operation of the central kitchen.
The contractor is Mestaripurkajat Oy, and the cost estimate is around 370 euros. The demolition work will be completed by the end of 000.
Weekly bulletins
Week 48: The frame dismantling phase of the object is complete. Next, we will continue with the demolition of the foundations and filling work.
The demolition of the upper parts and the asbestos work were completed on Thursday, and most of the demolition waste has been removed from the site. Concrete pulverization continues. Next week we will start crushing the concrete and continue lifting the foundations and pulverizing the concrete. The site strength is three machines, one asbestos worker and two handymen.

Week 45: Interior demolition work is underway on the front side of the building and the work was completed on Thursday. The personnel strength of the construction site is 5 people. Asbestos on the facades has also been removed. The water connection was completed for dust control. The electricity went out on Monday, the site electricity is now in use. Next week, the demolition work will start with two machines and the interior demolition will continue. The waste collection also begins. Next week, the site strength will be 7-9 people.
Week 44: Asbestos demolition work in progress in the first department and was completed on Thursday evening, the result of the clean air sample is awaited. The internal demolition continued with the collection of movables by three people. The personnel strength of the site is 5 people. On Monday of next week, a demolition machine and a few pallets will come to the site and we will start transporting stuff out of the inside. Asbestos removal continues with the demolition of facade minerals. Electricity will also be cut off from the property on Monday. Site electricity ready, waiting next to the fence.
Week 43: Internal demolition of the construction site is complete from the area to be partitioned and asbestos work is underway, about half of the floors have been sanded, the first asbestos partition will be completed at the beginning of next week. Employee strength 2 people.
For more information:
City structure manager
Erika Räihä
040 762 3811
erika.raiha@aanekoski.fi